Today's Test Specimen
Reports on the status of specimen fabrication and experimental preparation for NIED's independent and collaborative research will be provided as available (during the limited period when NIED independent and collaborative research experiments are being scheduled)
-
Feb 24,2026

Explanation
Preparations are ongoing for the open experiment in March. Today, interior wall panels are being replaced.
Last Updated:2026/02/24
-
Feb 10,2026

Explanation
Day 2 of the first series of shake table tests. With the cooperation of medical professionals, the conditions of medical facilities such as the NICU (Neonatal Intensive Care Unit) have been realistically recreated. While unexpected events occurred, all participants worked together to ensure the tests concluded successfully!
Last Updated:2026/02/10
-
Feb 6,2026

Explanation
Today, the first series of the experiments for the sub-project, “Study on Function Maintenance in Indoor Space during Earthquake” has commenced!
Last Updated:2026/02/06
-
Jan 27, 2026

Explanation
The test specimen for the “Study on Function Maintenance in Indoor Space during Earthquake” has been set up right on E-Defense shaking table after the New Year! Currently, interior work is in full progress in preparation for the shaking table experiments to be performed in coming February and March.
Last Updated:2026/01/27